Gold ore crushing production line has many configuration scheme. According to the different regions, gold ore's physical properties are different. Today, we introduce a simple machine configuration.
Production Situation
- The feed size: <400mm
- The finished product: 0-16mm
- The production capacity: 100T/H
Main Equipment
Now, we will a kind of gold ore crushing production line. Its production line can get up to 100T/H. we will use the gold ore crusher, including jaw crusher, cone crusher, hopper, vibrating feeder, vibrating screen, and a number of belt conveyors. I hope that this simple example is helpful for you.
NO. | Equipment | Model | Motor(KW) | Number |
1 | Hopper | LC3000*4000 | 1 | |
2 | Vibrating feeder | ZSW380*96 | 11 | 1 |
3 | Jaw crusher | PE600*900 | 75 | 1 |
4 | Cone crusher | HPC220 | 220 | 1 |
5 | Vibrating screen | 3YK2060 | 30 | 1 |

Production Line Process
Gold ore is delivered to the vibrating feeder by hopper. Then, it enters into the jaw crusher with uniform and quantitative through the vibrating feeder. Gold ore is in jaw crusher for the primary crushing. After extrusion and crushing, through the belt conveyor, gold ore is transported to the cone crusher for secondary crushing. Then, this gold ore is transported to the vibrating screen by belt conveyor. After screening, the material which meet the size requirement, become the finish product through the screen stencil. While the material which don't meet the size requirement, will again enter into the cone crusher for crushing. Through the vibrating screen, we can get the 0-16mm finished product. This will complete the production line process.
Related Equipment
Inquiry